8. CDM
and Health & Safety
Health & Safety Executive (HSE)
·
Aim to protect the health,
safety and welfare of employees, and to safeguard others, principally the
public, who may be exposed to risk from work activity
·
It aims to attribute the
responsibility of reducing risk to the people who are a best positioned to
reduce it in the different phases of a construction project.
·
This is implemented in three
ways
1.
Guidance documents – interpret
and help people understand the law
2.
Approved Codes of Practice –
offer practical examples of good practice
3.
Regulations – identify risk and
set our specific actions that must be taken to prevent
Regulations – CDM 2007 (updated in
2015)
·
Aim of CDM2007 is to integrate
health and safety into the management of the project and to encourage everyone
involved to work together to improve planning, identify hazards early on, target
effort and discourage unnecessary bureaucracy
·
The Construction (Design and
Management) Regulations (CDM Regulations) are intended to ensure that health
and safety issues are properly considered during a project’s development so
that the risk of harm to those who have to build, use and maintain structures
is reduced.
·
They were introduced in 1994
and came into force on 31 March 1995 following publication of European
Directive 92/57/EEC on minimum safety and health standards for temporary or
mobile construction sites.
·
In JCT SBC11, under clause 3.23
each party to the contract must agree to comply with all their obligations
under CDM regulations 2007. The
CDM co-codination and principle contractor are names under Articles 5 and
6. Clause 3.23.1 places a contractual
obligation on the Employer to ensure that the CDM co-ordinator is appointed.
Where projects are notifable (lasting
for longer than 30 days or 500 man hours) the client/ employers
responsibilities include:
Client / Employer obligation:
·
appoint a CDM co-ordinator
·
appoint a principal contractor
·
make sure that construction
work does not start unless a construction phase plan is in place and there are
adequate welfare facilities on site
·
provide information relating to
the health and safety file to the CDM co-ordinator
·
retain and provide access to
the health and safety file
Principle Contractor (usually the
General Contractor is appointed into the is role under JCT SBC11)
·
plan, manage and monitor
construction phase in liaison with contractor
·
prepare, develop and implement
a written plan and site rules (Initial plan completed before the construction
phase begins)
·
give contractors relevant parts
of the plan
·
make sure suitable welfare
facilities are provided from the start and maintained throughout the
construction phase
·
check competence of all
appointees
·
ensure all workers have site
inductions and any further information and training needed for the work
·
consult with the workers
·
liaise with CDM co-ordinator
regarding ongoing design
·
secure the site
CDM Co-ordinator (often the architect
is appointed this role)
·
The role of the CDM co-ordinator is to provide the client with a key
project adviser in respect of construction health and safety risk management matters. They should assist and advise the
client on appointment of competent contractor and the adequacy of management
arrangements
·
advise and assist the client
with their duties
·
notify details of the project
to HSE as soon as possible
·
co-ordinate health and safety
aspects of design work and co-operate with others involved with the project
·
facilitate good communication
between the client, designers and contractors
·
liaise with the principal
contractor regarding on-going design work
·
identify, collect and pass on
pre-construction information
·
prepare/update the health and
safety file
Architect Responsibilities
·
Provide information needed for
the health and safety file
·
Advice the client on their CDM
obligations ie. The appointment of a CDM co-oridnator at the outset of a
project.
·
When carrying out design work,
avoid foreseeable risks to those involved in the construction and future use of
the structure but eliminating hazards and reduce risk associated with hazards
that remain. The greater the risk
the greater the weight that must be given to eliminating of reducing it.
·
Encourage the Client to appoint
Principle Contractor as early as possible to help identify construction risks
in the design process, buildablity assessments and construction phase plan
·
Allow for sufficient time in
schedule for risk assessments, surveys etc
Health and Safety file - Prepared by the CDM
co-ordinator or updated if one already exists
·
A rolling file that provides
information allowing future works to the building to be carried out safety and
is a requirement under Regulation 10 of the CDM Regs.
·
The health and safety file must
be appropriate to the characteristics of the project and include a level of
detail proportionate to the risk
·
Normally keep for the life time
of the building and should be kept up to date
·
Contents includes:
·
Brief description of the work
carried out
·
Residual hazards
·
Key structural principles
·
Hazardous materials used
·
Health and safety information
regarding maintenance and cleaning
·
As-builts
Pre-construction information – Provided by the client to the design / contractor
·
Purpose of this is to provide
information for those bidding for or planning work and for the development of
the Construction Phase Plan
·
This is information in the
client’s possession, and passed on by the design team and CDM coordinator,
which is relevant to the construction work and is of an appropriate level of
detail proportionate to the risk involved.
·
The architect must take account
of the pre-construction information when preparing the design.
·
The approved code of practice
suggests this should include:
1.
Detailed description of the
project
2.
Clients consideration and
management requirements
3.
Environmental restrictions and
existing onsite risks
4.
Significant design and
construction hazards
5.
The Health and Safety file
Construction phase plan developed by the Principle Contractor
·
The construction phase plan
sets out how health and safety will be managed during the construction of the
project.
·
Construction phase plan is a requirement
of the CDM regulations 2007 and must be developed by the principal contactor
before any work on site can proceed to comply with Regulation 23(1).
·
The client needs to provide
enough time in the programme for this to be developed, therefore it is
advantageous to get a principle contractor on board as soon as possible
·
Should be specific to the
project, concise and easy to understand and should include:
1.
A description of the work
2.
Roles and responsibilities and
how the work will be managed
3.
Arrangements for controlling
significant site and health risks ie. Delivery and removal of material, dealing
with services, stability of structures, preventing falls, removal of asbestos,
reducing noice etc
4.
Pre-construction issues
5.
Assessment of risks
6.
Arrangements of managing risk
7.
Emergency procedures
8.
Circumstances under which risk
assessments or method statements should be prepared
9.
The Health and Safety File
Health and Safety at Work Regulations
1999
·
The main requirement on
Employers is to carry out a risk assessment. Employers with five or more employees need to record the
significant findings of the risk assessment
No comments:
Post a Comment