Negotiating planning
Question 01a.
List Site Specific Factor Summary
Due to these
site-specific factors, there are many legislative issues associated with
Development, Heritage and Preservation, environmental protection and
sustainability that will need to be considered.
Firstly, we
must consider the implications of the Town and Country Planning Act 1990, on
local planning policy.
Consideration of National Planning
Policy Framework
·
One of its primary objectives is to encourage
sustainable economic growth, making development easier. Considering
the proposal looks to develop the site which ………… in theory this type of
development would be supported in the local plan.
Consideration of the Local Plan
·
The Local Plan is guided by the NPPF 2012 and
is being rolled out to replace the LDF.
It establishes the specific planning policies in this area.
·
This
might give us guidance to the LA’s attitude to development and may….. insert
project specifics
Consultation with Local
Planning Authority (LPA)
·
We must ascertain the “use class “ of the
current site and determine if a change of use exists
·
Desktop research and pre-application advice from
LPA to understand planning history of site and attitude to development
·
Understanding of impact development may have
on neighbours. Planning consultant required
·
Public / community interest – major project?
Public consultation
Awareness of Conservation Area and
Listed Buildings requirements
·
Insert
scenario information
·
Listed Building/Conservation Area Consent is
required under the Planning (Listed Buildings and Conservation Areas) Act
1990.
Highways Act 1980
·
Changes
to the access to the site……
·
A civil engineer will need to be engaged, and
consultation with the highways authority to establish new access to the site if
needed.
Health and Safety at
works Act 1974 and CDM Regulations
·
The
site is directly adjacent to …….(insert text)
·
Contamination/ utility surveys undertaken at
early stage to full understanding of any potential health and safety issues.
·
A requirement of CDM 2007 Regulations that a
CDM Co-ordinator is appointed to carry out risk assessment of the site prior to
any soil surveys for contamination.
Environmental Issues
impacting the site
·
Consult the Environment Agency for relevant
surveys of flood risk. Relevant
legislation is PPS25 + Flood and Water Management Act 2010
·
Flood risk assessment – insurance/planning
issue
·
Area of Outstanding natural beauty + Green
Belts National Part and Access to Country Side Act
·
Environmental Protection Act – Bats etc
·
Area of Special Scientific Interest – Ancient
and Monuments and Archaeological Areas Act 1979
·
Sustainable Waste Management PPS 10
Optional: Land Law and Party Walls (Party Wall Act
1996)
·
Insert
Text about scenario
·
Investigation
of title deeds to establish boundaries, easements, rights of way and
restrictive covenants
·
Important
to establish boundaries to mitigate against the risk of disputes from neighbours
Optional: Building Regulations – Building Act 1984
·
A
full building Regulations application will be required under The Building Act
1984 and the Regulatory Reform Order 2005 regarding fire regulations.
Impact on timing of
project:
Public Consultation
·
Insert
project specifics
·
We anticipate a high level of community
interest in this development
·
Recommend engagement with planning consultant
to help identify areas of the scheme that might be contentious and help with liaising
with the LPA and through the public consultation period to gain local body buy
in and feedback, reducing the risk of issues down the line.
Conservation Consultant
·
If
conservation consent is require this will have a huge impact on the potential
development of the site.
·
Early
consultation from English Heritage, conservation officer would be highly
recommended.
Access Consultant
·
As the current building appears to be
accessed …….(insert text) new access may need to be defined and integrated into
the existing traffic infrastructure.
·
Consultation with an Access Consultant recommended
to develop a Design and Access statement (DAS), needed to be produced to accompany
the consent application.
Consultation
with Utilities companies
·
May require negotiation and formal agreement
with utility companies for alterations to the existing electrical substation
which is potential time risk to progress.
Detailed
Planning Application
·
If
change of use, it must be a full application
·
8
weeks typically – 13 weeks if considered a major project
·
16
weeks if there is an environmental statement
·
valid
for 3 years
Refer Ed notes for diagram
Possible
Questions 01 B
Outline
Planning Application
·
Outline
planning applications can be used to find out whether a proposed development is
likely to be approved by the planning authority, before substantial costs are
incurred developing a detailed design. Outline planning applications allow the
submission of outline proposals, the details of which may be agreed as
'reserved matters' applications at a later stage.
As a minimum outline, planning applications should
include information on:
·
The
uses proposed for the development and any distinct development zones.
·
The
amount of development proposed for each use.
·
The
indicative layout.
·
An
indication of the minimum and maximum height, width and length of proposed
buildings.
·
Areas
in which access points to the site will be located.
·
For
most applications – Design and Access Statement
Reserved
Matters
·
Appearance
·
Means
of Access
·
Landscaping
·
Layout
·
Scale
Detailed
Planning Application
·
If
change of use, it must be a full application
·
8
weeks typically – 13 weeks if considered a major project
·
16
weeks if there is a environmental statement
·
valid
for 3 years
Refer Ed notes for diagram
An explanation of what information
would be required for the planning application and the timeframe for the
planning approval.
·
Considering the above UK legislation
requirements and their potential effect on the scheme considerable time must be
allowed for the process of consultation and formal application to gain planning
approval for your proposed development.
·
Time must be allowed for the following steps
before the planning application can be submitted.
·
Preliminary investigation and pre-application
advice
·
Public Consultation
·
Preparation of the planning application
·
Processing the application. For a standard planning application this
timeframe for a decision is 8 weeks. If
the LA considers this a major project the timeframe planning application
decision increases to 13 weeks.
·
Application for Listed Building Consent if
required. (Can be applied concurrently with planning)
·
Pre-application advice could inform us
whether Section 106 agreements will be required. This will involve considerable negotiation
over the social better provisions that the local authority will require as a
result of approving the proposal, and the CIL will also be relevant.
·
The planning consent may also be approved
with conditions that will need to be discharged before building works can
begin.
·
Negotiations with the utility companies, if
carried out promptly, may run concurrently and not affect the overall
·
If the planning application is refused an
appeal can be made or a revised application can be submitted within 12 months
at no extra change. There are 3 methods
to appeal – written submission, informal hearing or public enquiry and can take
between 3-6 months from the time the appeal is made.
Pre Application Advice / Planning
History
The size of
the project along with the anticipated public interest associated with proposed
development will mean that the planning application process must be carefully
managed and factored into the overall project programme. The Client has already engaged with the local
Council in preliminary discussions but it would be wise to follow this up with
further pre-application advice from the Local Planning Authority. Preparation of specialist reports.
Public Consultation
The site is
adjacent to a large residential area and open park space. Therefore, time must be set aside to address
possible local concerns regarding change of use, increased traffic volume,
noise associated with the development of a football stadium. These issues could be raised and address
through public consultation.
Planning Application
Time must
also be allowed for the development of the design and preparing of the planning
application. Although the normal
planning approval process should take 8 weeks, it is expected that this project
would be considered a Major project, requiring a longer approval process of 13
weeks should also be factored into the project schedule.
Section 106 Agreement Negotiation
As the
project is significant, and the local council has already indicated that they
may have some requirements for additional public open space, it is likely that
a Section 106 Agreement (TCPA 1990) will also be required. This will involve considerable negotiation
over the social betterment provisions that the local authority will require as
a result of approving the proposal and the Community Infrastructure Levy will
also be relevant
Planning Application Refusal / Appeal
Because of
the large and complex nature of the development it hard to put a defined time
on this process and the possibility that the application will be approved with
conditions that need to be discharged or the application is rejected (requiring
appeal or resubmission) will need to be factored into the overall project
schedule.
Information Required for Planning
·
Covering letter
·
Application Fee
·
Agricultural / Ownership Certificates
·
Drawings including Site Plan
·
Design and Access Statement
·
Supporting statements ie. Transport
assessment, retail impact assessment Environmental Impact Assessment
Information Required for Listed
Building Consent
·
Drawings
·
Details may also be required
·
Survey
·
Heritage Statement
·
No fee required
·
Refer to the LA requirements
Building notice
·
On
small projects, or when changes are made to an existing building, approval may
be sought by giving a 'building notice'. In this case, a building inspector
will approve the works as they are carried out by a process of inspection.
·
A
building notice application can be made with a simple application form, a site
plan (if an extension is involved) and the appropriate fee (calculations may
also be required for certain aspects depending on the complexity of the
project). This means that work can begin very quickly, and need not necessarily
involve design consultants.
·
However,
a building notice application leaves the client at risk that completed works
might not be approved, resulting in remedial costs.
Full plans submission
·
Generally
on larger, new-build projects, a 'full plans' application will be made, meaning
that full details of the proposed building works are submitted for approval
before the works are carried out.
·
Full
plans approvals are also subject to inspection during the course of the works,
but as long as the work is carried out in accordance with the approved design,
the risk of problems is very much lower than for a building notice application.
No comments:
Post a Comment