Procurement:
Possible procurement routes:
Traditional (general
contracting)
Design and Building
Management
contracting
Construction
management
·
Complexity
and scale of project
·
Analysis
the client’s attitude to risk
·
Certainty
on cost , completion time, quality
·
Architects
experience vs contractors involvement in design
·
Risk
should rest with whoever can manage it best.
Notes Example:
·
In regards to this scenario, the choice of
procurement route should reflect the complexity and scale of the project……..(insert project specifics)
·
The Clients past experience in the delivery of
projects of this scale are…….. (insert
past experience)
·
The client has expressed that time or/cost/or quality is of highest
importance to them.
·
Our experience with design services of this
scale is……(insert specifics).
Requiring contractor involvement at (insert
specifics) time of the project
·
Therefore the procurement method selected should
allow the design and construction risk to rest with whoever can manage it best.
Traditional Contract
(general contracting)
·
The architect would prepare design and contract
documentation and assist the client in selecting a contractor by competitive
tender or negotiation.
·
The contractor awarded the work would agree to
complete the construction to the contract documents for a contract sum.
·
With a traditional Contract, a contract
administrator is appointed (commonly the architect) to administer the contract
impartially and the client has a mechanism to alter the design through
variations, which may or may not alter the final construction cost and date of
completion.
·
Areas that require specialist sub-contractor
input could be facilitated through Contractors design proposals (CDP’s)
Advantages
·
Clear cut division between design and construction
·
Level of time and cost certainty from the tender
stage. Employer retains control of
quality and takes on the risk of variation costs.
·
Contractor assumes responsibility for
construction and takes on financial risk for this.
·
Client assumes responsibility for design team
and takes on their performance risk.
Negatives
·
With control comes a level of risk with the risk
of the final construction cost largely remaining with the client.
·
Late changes affect cost and programme
·
Design must be very progressed to tender the
design and get surety on construction costs.
Therefore, could be considered a relatively slow form of procurement
with time needed up front to properly define the design requirements.
·
Contractor not known during the design phase,
hence note available for consultation.
These can be somewhat combated by the inclusion of CDP’s for limited
contactor design input.
Notes Example:
The advantage of the use of the contract is that the client
will maintain a high level of control on the design, even when the project
moves to site. Using SC2011 as
reference, clause 3.14.1 allows for the client to make variations to the design
through the construction process through issuing variation orders. The final construction cost can be altered to
absorb these changes. However, with
control comes a level of risk with a disadvantages of this method of
procurement is the risk of total construction cost largely remains with the
client. Although a lump sum will be
agreed when the contract is signed this lump sum is subject to fluctuation in
price if variations occur.
Design and Build –
JCT DB
·
Using a Design and Build (D+B) Contract the
client would appoint a Contractor to “design and Build” the project.
·
Assuming the design team has already been
appointed the most appropriate form of D+B contract would be one that notated
the current design team, through a Deed of Novation, to the contractor once the
Employers Requirements (ER’s) have been produced.
·
The contractor would take the full design risk /
responsibility for implementation of the Contractors Proposals (reflecting the ER’s)
·
The client can expect to pay a premium for the
Contractor taking on this risk which may materialise in the form of higher
construction cost compared with a traditional contract.
Advantages
·
Package deal – Client can unload more risk and
control
·
Employer has one point of reference.
·
Design and Construction integrated within one
accountable organisation
·
Relatively fast design and construction process
with construction proceeding in parallel.
·
Guaranteed cost and completion date
Disadvantages
·
Employers requirements need to be robust to
ensure the level of quality meets the clients expectations and maintains cost
certainty
·
Less competitiveness
·
No independent administrator (hence less quality
control)
·
Employer has no say in specialists
·
Not in contractors interest to spend time on
design.
Notes Example:
As the main disadvantage to this
procurement route in relation to the Cancer Center Project is the loss of
control the client will experience by passing the design responsibility over to
the contractor. Although act gives price
surety to the project, the client will have little control to vary any design
element which is outside that stipulated in the Employers requirements. This procurement route has the advantage of
giving the Client both cost and time surety for the project completion but may
not give them enough control on the quality of the final product.
Management
·
With this method of procurement the Client would
appoint a Construction manager along side the design team. The management contractor would be
responsible for defining packages of work and then managing the carrying out of
this work through separate trades or work contracts.
·
Management Procurement can take varied forms.
Two of which are:
·
Management
Contactor: JCT MC
·
Client appoints a management contractor who is
responsible for managing the carrying out of the work and appointing works
contactors to undertake the work.
·
Construction
management Appointment: JCT CM/A + JCT CM/TC
·
The trade contractors are appointed directly by
the client meaning the client is directly and contractually responsible to the
trade contractors. The client therefore
assumes a major role in directing the project, whilst leaving the management of
it to the construction manager.
Advantages
·
The advantage of the Management procurement
route is that the client retains overall design control through the
professional team.
·
Detailed design can proceed in parallel with
construction work and much of this might be of a specialist nature relating to
specific packages. As a consequence an
early start on site is often possible, and time for the project may be reduced
overall.
·
Design changes are possible as construction
proceeds, always provided that the changes do not affect work packages already
let do as to result in abortive work.
Disadvantages
·
There is no certainty over cost at the outset
and work proceeds on the basis of the contract cost plan.
·
The client will need to appoint a contract
administrator as part of the professional team
·
Speculative risk are largely with the client and
this procurement method call for a measure of trust, goodwill and in-house
expertise. In terms of design and
quality, it is a relatively low risk option for the client but there is
generally a higher risk in respects to cost and time.
Recommending
Traditional Contract:
·
In this scenario we would recommend to the
client a traditional (general contracting) procurement method using a JCT SBC2011 contract with quantities.
·
As the client has identified that they wish to
be fully involved in the deliver of the construction project, the traditional
approach allows for a level of cost and
time surety through a competitive tender process but also allows for a
mechanism for client driven variations to the design through the construction
process.
·
With design
control, the client’s allocation of risk
regarding cost and extensions to the construction schedule is higher than a D+B
Contract, however; from the information given it is clear that the budget
and construction is secondary to the clients requirements for a quality state
of the art center as a result.
·
The architects
experience are known to specialise in the design of healthcare facilities
so will have prior experience in the design challenges that come with
this. Therefore, it may not me necessary
to have contractor involvement from
the early stages of the design (unlike the advantages of a management
procurement route) and any
·
Specialist
sub-contractor design elements could be deal with through CDP’s. As it is stated that the client does not have
a deadline for the building to be completed by,
it appears that a two stage tendering process would not necessary,
allowing a more competitive tender result.
Possible Questions:
Architects role in
traditional procurement method
With a traditional procurement route selected, it is likely
that the architect will fill the role as administer of the construction
contract. The contract administrator’s
duties to the employer are normally set out in an appointment and the role
requires that administration of the construction contract impartially. Key duties include:
·
Inviting and processing tenders.
·
Preparing contract documents for execution.
·
Administrating change control procedures.
·
Seeking instructions from the client in relation
to the contract.
·
Issuing instructions such as variations, or
relating to prime cost sums or making good defects.
·
Considering claims.
·
Chairing construction progress meetings.
·
Preparing and issuing construction progress
reports.
·
Co-ordinating and instructing site inspectors.
·
Agreeing commissioning and testing procedures.
·
Agreeing defects reporting procedures.
·
Ensuring that project documentation is issued to
the client.
·
Issuing certificates of practical completion and
interim certificates.
·
Collating and issuing schedules of defects.
·
Issuing the certificate of making good defects.
·
Issuing the final certificate
Our it would be anticipated that the architects services
agreement will also include a duty to visit the construction works. This role is also reinforced by the RIBA and
ARB Code of Conduct standard 6.
Tendering
Three methods:
Single Stage
Two Stage
Negotiated
Single Stage
tendering
·
Single-stage tendering is the more traditional route,
used when all the information necessary to calculate a realistic price is
available when tendering commences:
Process
·
An invitation to tender is issued to prospective
suppliers (perhaps following completion of a pre-qualification questionnaire
and / or a pre-tender interview). The invitation to tender will include
information describing the goods or services required in sufficient detail to
enable prospective suppliers to prepare an accurate tender.
·
Tenders are prepared and returned by prospective
suppliers (this may involve questions and answers and a mid-tender interview to
clarify the client’s requirements).
·
Submitted tenders are then assessed and compared
The preferred tenderer is selected and negotiations opened.
·
Subject to the outcome of those negotiations the
preferred tenderer may then be appointed.
Two Stage tendering
·
Two-stage tendering is used to allow early
appointment of a contractor, prior to the completion of all the information
required to enable them to offer a fixed price.
·
In the first stage, a limited appointment is
agreed allowing the contractor to begin work and in the second stage a fixed
price is negotiated for the contract.
·
An also be used in Design and Build contracts
Negotiated
·
Negotiated tendering occurs when the client approaches
a single supplier based on their track-record or a previous relationship and
the terms of the contract are then negotiated.
No comments:
Post a Comment