Saturday, January 3, 2015

07_CDM Regulations


Index:

 

·         Limitation Periods

·         Content of Contract

·         Collateral Warranties

·         Building Regs and Control

·         Building Notice

·         Full Plans Submission

·         Novation

·         Valuing of Site Materials

·         Provisional Sums

·         Prime Cost Sums

·         Employers Requirements and Contractors Proposals

·         Insurance Options

·         Extension of Time

·         Retentions

·         Liquidated damages

·         Architects Instruction

·         Variations

·         Relevant Matters

·         Relevant Events

·         Loss and Expense

·         Payment and non payment

·         Practical Completion

·         Partial Possession

·         Certificate of Non-Completion

·         Rectification Period

·         Final Certificate

·         Latent and Patent Defects

·         Termination

·         Role of Contract Administrator

 

 


 

Glossary

 

Limitation Periods

 

·         A limitation period is a time period after which liability is extinguished and court action cannot be taken.

·         In a negligence claim, time will usually run for 6 years from the date when the negligent act or omission caused damage to occur

·         In a claim based on a contract executed under hand, the limitation period is 6 years, running from the date when the contract was breached.  The period is extended to 12 years if the contract was executed as a deed and the limitation period runs from the date when the contract breach happened. 

·         The Limitation Act 1980 makes it is possible to bring a claim outside the 6-year limitation period for latent damage (damage which was not reasonably discovered before the expiry of the basic 6-year limitation period).  In these circumstances the limitation period is 3 years from the date on which the claimant had knowledge of the damage to a maximum of 15 years.

·         Under clause 2.19.1 of SBC11, the Contractors liability for the contract’s design portion is equivalent to that of the Architects design portion. If the design is found to have failed within the liability period then the Contractor can be sued for Negligence if it can be proven that the contractor failed to design this portion using reasonable skill and care.

·         Professional indemnity Insurance – the Contractor is required to carry PP! (clause 6.12), the level and amount of cover must be inserted in the contract particulars.  Default Limitation period is 6 years but is usually changed to 12 years from Practical completion.

 

·         Example: Limitation periods are relevant to the Cancer Treatment job as they will be a condition of the Architects appointment.  The architect must ensure they have appropriate PII insurance to protect the firm against any potential claims of negligence or breaches in contract for the full liability period.  If, for example, if 3 years after practical completion cracking and subsidence is discovered in a corner of the building.  After further investigation it is discovered that the design of the foundations were insufficient, the architect could still be sued for the fault of the design as a negligent act as it is within the 6 year liability period.

 

Content of a Contract

·         The rights and obligations of parties to a contract are defined by its terms.

·         Express terms are those that have been explicitly agreed by both parties and can be oral or in writing.

·         However, the express terms do not always constitute all the relevant terms of the agreement. In certain circumstances, Implied terms exist and can be upheld by the courts if the implied terms are necessary to give business efficacy to the agreement.

·         Ie. Implied term implied by previous course of dealings between the parties.

·         Implied by statue ie. Goods and services Act, if not agreed, it will be implied that s.13 services will be provided with reasonable skill and care /reasonable time / reasonable price paid.

 

 

Collateral Warrenties

 

·         Due to privity of contract, only parties to a contract are bound by its terms.  This means that the terms of the contract can not generally be enforced by or against someone who is not party to it. Construction projects often require a network of Collateral Warrenties to be put in place, which extend terms set out in a contract to third parties who have a vested interest in successful execution of the contract.

 

·         A Collateral Warrenty is affectively a separate contract between the relevant member of the project team and an third party (for example 3rd party funder) including them the same rights to make claims under the contract.

 

·         In architectural appointments, Architects should avoid collateral warranties where possible and if required should never agree to greater liability under the collateral warranty than in their appointment in scope, quantum or duration.

 

·         Similar to the effects of a Collateral Warrenty, another way that the terms of a contract can be passed on to a third party not privy to the original contract is through a specific term written into the contract which has been allowed through the Contracts (Rights of Third Parties) Act 1999.  This Act allows for the naming of a group or specified third parties which the terms of the agreement are extended to. However, this act has to be included into the contract terms and is not a universal right.  Many contracts exclude the Act, for example the RIBA Standard Conditions of Appointment (clause 7.8)

 

·         A typical example would be where an architect of a new office development owes a duty of care to an occupier of the development in so far as any subsequent defects which may arise are concerned. Privity of contract rules would prevent any liability arising between the architect and occupier without the existence of a collateral warranty.

 

Building Regulations + Control

 

·         Under the Building Act 1984, building control has been delegated as a function to the local authorities, through either building controlled officers or approved inspectors.

·         They are delegated to make sure buildings which fall under the Act are in line with this legislation and the Building Regulations 2010.

·         The building Regulations 2010 is a form of Building Approval Legislation. The documents exist to secure the safety, sustainability and durability of design.  They also check the suitability of building methods and materials used.

 

·         EXAMPLE: When planning the internal layout of the large new-build office building, it was important that fire safety should be considered to coincide with Part B of the Building Regs 2010.  Part B1 says that the building shall be designed and constructed so that there are appropriate provisions for the early warning of fires and appropriate means of escape from the building to a place of safety.

 

Novation

 

·         A novation is a three-way agreement made by the original employer, an incoming employer and the architect (or other service provided) under which the architect appointment is transferred from the original employer to the new employer so that after the novation the architect carries out their duties for the benefit of the new employment and is paid by the new employer.  This is usually undertaken through a deed of novation.

 

·         A novation agreement is not possible without consent. If novation and the form of novation agreement were not agreed when the consultant’s was initially appointed, they are under no obligation to agree to be novated. It is essential therefore that the principal contracts between client and consultants and between client and contractors contain express terms obliging the contractor and the consultant to enter into the novation agreement.

 

·         Example: This is relevant to the Cancer Treatment Center appointment, especially if the client chooses a Design and Build procurement route.  If the architect is aware that this procurement route is favourable to the client, they should ensure that the terms of the novation are discussed and agreed to at the outset, and what the terms of any on-going agreement to provide service to the client will be.  There are two types of novation – a basic switch from client to contractor and a “ab initio” where the new employer is deemed to have been the architect client from the outset.  The second type of novation should be avoided.  If there is a significant risk that the party to whom the architect will be novated does not have a sufficiently strong financial covenant to pay the architects fees then the architect should not go through with the novation.

 

 

 

Building notice

·         On small projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.

·         A building notice application can be made with a simple application form, a site plan (if an extension is involved) and the appropriate fee (calculations may also be required for certain aspects depending on the complexity of the project). This means that work can begin very quickly, and need not necessarily involve design consultants.

·         However, a building notice application leaves the client at risk that completed works might not be approved, resulting in remedial costs.

 

Full plans submission

·         Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out.

·         Full plans approvals are also subject to inspection during the course of the works, but as long as the work is carried out in accordance with the approved design, the risk of problems is very much lower than for a building notice application.

 

 

 

 


 

 

Valuing Off-Site Materials

 

·         In clause 4.16.1.3 of JCT SBC11 allows for Listed items to be included in Interim Payment Certificates.  This means that if the contractor intents to purchase material in advance and store them off site, the cost of these items can only be claimed in interim certificates if the items were named in the Contract by means of a list attached to the bill of quantities.  The Contractor must provide proof that the items are insured and are set apart or clearly marked and identified (cl4.17.3).

 

·         Other than items that are listed, the CA has no power to approve payment to any off-site materials.  This clause is in place to protect the interests of the Employer in the event that the Contractor becomes insolvent

 

Provisional Sums

 

·         A provisional sum is an allowance, usually estimated by the cost consultant, which is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to price.  This, together with a brief description, allows tenderers to apply mark up and attendance costs within their overall tender price and make allowance for the work in the contract programme.

 

 

·         An example of a situation where a provisional sum might be appropriate is when work is required below an existing structure, where the ground conditions cannot be determined until the existing structure is demolished and the ground opened up.

 

·         In a JCT SBC11, under SMM7, Provisional sums can be 'defined' or 'undefined':

 

·         Defined provisional sums are considered to have been accounted for within the contractor's price and programme. In effect the contractor is taking the risk that their estimate will be sufficient.

 

·         Undefined provisional sums are not accounted for in the contractor's price and programme. This means that the client is taking the risk for the works and the contractor may be entitled to an extension of time and additional payments.

 

·         Provisional sums place either the contractor or the client at risk of unexpected costs or delays. Agreeing the cost of such work or extensions of time that might be claimed can result in tension between the contractor and client. For this reason, they should only be used as a last resort, they should not be an easy fall-back position for consultants (who are not bearing any of the risk) when designs are incomplete or information is difficult to obtain.

Prime Cost Sum


·         A prime cost sum is an allowance usually calculated by the cost consultant for the supply of work or materials to be provided by a contractor or supplier that will be nominated by the client. The allowance is exclusive of any profit mark up or attendance (such as material handling, scaffolding and rubbish clearance etc) by the main contractor.

·         JCT SBC11 Clause 3.8 allows for – listed sub-contractor

·         JCT intermediate contract allows for Named Specialists.

 

 

Employers Requirements and Contractors Proposals

 

·         Employer's requirements are typically used on design and build projects (such as Joint Contracts Tribunal (JCT) BD 05) or on a traditional contract where the contractor is to design discrete parts of the works. They provide a description of the client's requirements, including; the specification for the building, the scope of services required from the contractor and an allocation of risk for unknown items. Contractor's proposals are then prepared in response to the employer's requirements. These present the contractor's suggested approach for designing and constructing the building, along with their price. 

·         In a traditional contract, for example JCT SBC11, employers requirements are prepared if it there are elements of the design that require specialist contractor input.  The contractors design obligations are set out under clause 2.2 (JCTSBC11- with quantities).  In contractor will submit a proposal containing a design solution with its tender (the contractors proposals, eleventh recital).   The Contractor is liable for designs under the contractors proposals and should maintain suitable PII to cover this design work.

 

·         The level of detail in the employer's requirements and the extent of design required from the contractor is very variable. Employer's requirements can range from a very simple specification to a fully developed performance specification and concept design.

 

·         The employer's requirements is a very important document as, although it is prepared early in the project, it defines the success of the outcome. The better prepared they are, the keener the price from the contractor and the less likely there will be disputes. If the employer's requirements are not properly developed, the client can incur significant additional costs, as any requirements which are not properly specified, or are changed, will require the issue of instructions for which the client will be charged by the contractor.

Insurance Options


·         On a construction site it is important that liability for losses resulting from personal injury or damage to any property or to the works are allocated to a party, and that the liability is backed up by insurance.

·         The under clause 6.1-6.3 the contractor is responsible to indemnify against the risk of injury to persons and damage to property other than the works, which are the result of the works.  The minimum cover is entered into the contract particulars.

·         There are 3 options for covering insurance in the works and are set out in schedule 3:

·         Option A – insurance is taken out by the contract and is for the full reinstatement of the Contract works, including professional fees

·         Option B- insurance is taken out by the Employer, and if for the full re-instalment values of the works including professional fees

·         Option C – applicable when the work is being carried out to an existing building.  It includes two insurances, both taken out by the Employer.  The existing structure and contents must be insured against “specified perils” as defined in Clause 6.8.  New works in, or extensions to, existing buildings must be covered by an “All Risks” insurance policy.

·         Options A and B are for insuring new building work and require “All risks” cover under joint names policies.

 

Extension of Time

 

·         Many construction contracts allow the construction period to be extended where there are delays that are not the contractor's fault. This is described as an extension of time (EOT).

 

·         Under JCT SBC11, the granting of extensions of time are set out under clause 2.26-2.29.  When it becomes apparent that there is a delay that could merit an extension of time, the contractor must give written notice to the CA.  This notice should set out the circumstances and cuase of the dealy and identify any relevant events for the cause.  The CA must respond within 12 weeks, with a decision either fixing a new completion date or notifying the contractor that no extension of time is due (cl 2.28.2)

 

Relevant events may include:

·         Variations.

·         Exceptionally adverse weather.

·         Civil commotion or terrorism.

·         Failure to provide information.

·         Delay on the part of a nominated sub-contractor.

·         Statutory undertaker’s work.

·         Delay in giving the contractor possession of the site.

·         Force majeure (such as an epidemic or an 'act of God').

·         Loss from a specified peril such as flood.

·         The supply of materials and goods by the client.

·         Strikes.

·         Changes in statutory requirements.

·         If the works are not completed by the completion date set out in the contract and no extension of time claims are yet to be settled, the CA is required to issue a certificate of non-completion, and the client can advice the Contractor that they will claim for liquidated damages, at the rate set out in the contract.

 

·         Delays in receiving permissions that the contractor has taken reasonable steps to avoid.

·         The contractor is required to prevent or mitigate the delay and any resulting loss, even where the fault is not their own.

 

·         All claims should be judged against the progress of the works and not the programme and must demonstrate the link between the breach (cause) and the delay.

·         Mechanisms allowing extensions of time are not simply for the contractor's benefit. If there was no such mechanism and a delay occurred which was not the contractor’s fault, then the contractor would no longer be required to complete the works by the completion date and would only then have to complete the works in a 'reasonable' time. The client would lose any right to liquidated damages.

Retentions

 

·         Retention is a percentage (default is 3% but standard requested by clients is now 5%) of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due and retained by the client. The purpose of retention is to ensure that the contractor properly completes the activities required of them under the contract. Retention can also be applied to nominated sub-contractors, and the main contractor may also apply retention to domestic sub-contractors.

 

·         Half of the amount retained is released on certification of practical completion and the remainder is released upon certification of making good defects (or 'final statement' for design and build contracts such as Joint Contracts Tribunal (JCT) DB 05).

 

·         Interim certificates should make clear the amount of retention and a statement should also be prepared showing retention for nominated sub-contractors.

 

·         In some cases, it may be agreed that a bond is held by the Employer in lieu of retentions,  JCT SBC11 makes provision for this in clause 4.19.  The bond has a similar effect by giving the Employer insurance that the contractor will properly complete their requirements under the contract.  When clause 4.19 is applied, retentions is not deducted from amounts on the certificate.

 

·         NB. On construction management contracts, a separate certificate of practical completion must be issued for each trade contract and so there are a number of defects liability periods. This means that retention must be released as required for each individual trade contract. The same is true on management contracts, where each works contract must be certified individually.

 

Liquidated Damages

 

·         Contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LAD's) to the client in the event that the contract is breached.

 

·         In JCT SBC11 the agreed rate of liquidated and ascertained damages for the works is set out in the contract particulars.  This is normally expressed as a specific sum per week of delay, to be owed by the Contractor in the event of failure to complete the works by the completion date.  In this event, the CA is required to certify the non-completion by means of a Non-Completion Certificate (set out in clause 2.31)

.

·         Under Clause 2.32.2 the Employer must notify the Contractor before the date of final Certificate that he may require payment of liquated damages if the completion date is not achieved.  Once the non-completion certificate has been issued, the contractor is said to be in ‘culpable delay’ and the Employer can advice the Contactor to their intent to deduct liquidated damages from the next interim certificate.

 

·         Liquidated damages are not penalties, they are pre-determined damages set at the time that a contract is entered into, based on a calculation of the actual loss the client is likely to incur if the contractor fails to meet the completion date. They might include, rent on temporary accommodation, removal costs, extra running costs and so on.

 

·         If the project is delayed by an event that impacts on the completion date, but is not the fault of the contractor, then this may constitute a 'relevant event' for which the contractor may be granted an extension of time (ie the completion date in the contract is adjusted), A relevant event might be a delay that is caused by the client, or a neutral event such as exceptionally adverse weather.  Under Clause Under JCT SBC11, the granting of extensions of time are set out under clause 2.26-2.29.  If an extension of time claim is accepted by the CA, the completion date will be pushed out accordingly and liquidated damages can not be claimed unless the works are not completed by the new date set.

 

·         Mechanisms allowing extensions of time are not simply for the contractor's benefit. If there was no such mechanism and a delay occurred which was not the contractor’s fault, then the contractor could no longer be required to complete the works by the completion date and would only have to complete the works in a 'reasonable' time. With no enforceable completion date, the client would lose any ability to claim liquidated damages.

Architects Instruction


·         JCT SBC11 clause 3.10 gives the contract administrator the power to issue instructions to the contractor. These instructions can be called ‘contract administrator’s instructions’ or ‘architect’s instructions’ (AI's).

Broadly speaking, an AI may be given for the following reasons:

·         To vary the works.

·         To postpone the works.

·         To remedy workmanship, goods or materials which are not in accordance with the contract.

·         To sanction a variation made by the contractor.

·         In relation to the expenditure of provisional sums.

·         To open up work for inspection.

·         To carry out tests.

·         To exclude persons from the site.

Provisions for Variations


·         A variation is an alteration to the scope of works in a construction contract in the form of an addition, substitution or omission from the original scope of works.

 

A variation may include:

·         Alterations to the design.

·         Alterations to quantities.

·         Alterations to quality.

·         Alterations to working conditions.

·         Alterations to the sequence of work.

 

·         Variations may also need to be made when the contract documents do not properly describe the works actually required.

 

·         In JCT SBC11, the Contract Administrator has the power to order specific variations under clause 3.14.1, and the scope of what constitutes a variation is set out in clause 5.1.

 

·         All variations under clause 3.14.1 may result in an adjustment of the contract sum (Clause 4.3.1) and could result in a claim for extension of time (cl2.29.1) or direct loss and/or expense (cl.4.24.1). 

 

·         The CA cannot issue variations after practical completion.

 

Relevant Matters


·         A relevant matter is a matter that the client is responsible that effects the progress of the works. This may enable the contractor to claim direct loss and / or expense that has been incurred.

·         Clause 4.24 sets out 5 situations when a claim can be made caused by relevant matters

Relevant matters might include:

·         Failure to give the contractor possession of the site.

·         Failure to give the contractor access to and from the site.

·         Delays in receiving instructions.

·         Opening up works or testing works that then prove to have been carried out in accordance with the contract.

·         Discrepancies in the contract documents.

·         Disruption caused by works being carried out by the client.

·         Failure by the client to supply goods or materials.

·         Instructions relating to variations and expenditure of provisional sums.

·         Inaccurate forecasting of works described by approximate quantities.

·         Issues relating to CDM.

 

·         A relevant matter need not necessarily result in a delay to the completion date, and so may not always entitle the contractor to an extension of time

 

Relevant Events


·         Relevant event is an event that causes a delay to the completion date, which is caused by the client, or is a neutral event not caused by either party.

·         Clause 2.29 sets out 14 situations when a claim can be made caused by relevant events

·         Examples include: Variations, late possession of site, expectional adverse weather.

·         Relevant events entitle the contractor to claim an extension of time; that is for the completion date to be moved. A relevant event does not necessarily entitle the contractor to claim loss and expense.

 

Loss and Expense


·         Clause 4.23 gives provision for the contractor to claim direct loss and / or expense as a result of the progress of the works being by relevant matters which the client is responsible, such as:

·         Failure to give the contractor possession of the site.

·         Failure to give the contractor access to and from the site.

·         Delays in receiving instructions.

·         Opening up works or testing works that then prove to have been carried out in accordance with the contract.

·         Discrepancies in the contract documents.

·         Disruption caused by works being carried out by the client.

·         Failure by the client to supply goods or materials.

·         Instructions relating to variations and expenditure of provisional sums.

·         Inaccurate forecasting of works described by approximate quantities.

·         Issues relating to CDM.

 

·         Claims may comprise costs resulting from disruption to the works or from delays to the works (prolongation).

 

·         The contractor must give written notice of a claim as soon as it becomes reasonably apparent that the regular progress of the works is being materially affected.

·         Direct losses are those that 'flow naturally' from the breach of contract.

 

 

 

Provisions for payment and non-payment


 

·         One of the most important duties of the CA under SBC11 is the issuing of certificates of payment

·         In JCT SBC11, the contractor is entitled to periodic payments through the issuing of interim certificates.  The “due dates” are defined in the contract particulars the (first one entered then subsequent on a one-month basis).  In clause 4.10.1, Interim certificates are required to be issued within 5 days of the due date and payment made within 14 days of the due date (Clause 4.12.1).

·         The valuation of interim certificates can be made by two methods, acceptance of the Contractors application for payment, or valuation by the QS.

·         The CA should only certify interim certificates after having carried out an inspection, and should not include work that appears not to have been properly executed.  If work is included and then is later found to the defective, the value can be taken off the next certificate.

·         A percentage (3% as default but standard 5%) of the money owing is deducted from the interim certificate as a Retention.

·         In clause 4.12.5, If the employer intends to withhold an amount from the sum certified in the certificate, then the contractor must be given notice before the final date of payment in the form of a ‘Pay Less Notice’ which will set out the sum and the basis which that sum has been calculated.

 

·         Refer diagram Page 110 – guide to SBC11.

 

Practical Competition


·         The contract administrator certifies practical completion when all the works described in the contract have been carried out as per clause 2.30 of JCT SBC11.

This certificate should be issued only when, in the CA’s opinion, the following three things have been done:

·         Practical completion of the works

·         Contractor has supplied as-built drawings for the CPD section of works (as per clause 2.40)

·         The contractor has supplied all information for the health and safety file (as per clause 3.23.4)

 

Certifying practical completion has the effect of:

·         Releasing half of the retention (an amount retained from payments due to the contractor to ensure that they complete the works).

·         Ending the contractor's liability for liquidated damages (damages that become payable to the client in the event that there is a breach of contract by the contractor - generally by failing to complete the works by the completion date).

·         Signifying the beginning of the defects liability period.

 

Partial Possession


 

·         It is possible for the Employer to gain possession of a portion of the project with the agreement of the Contractor.  Partial Possession is set out in Clause 2.33-2.37 of the JCT SBC11.

·         When practical completion is deeded to have occurred for the relevant part of the works, the rectification period for that part of the works starts and the certification of making food defects has to be issued for that part separately.  

·         Under clause 2.37 Liquidated damages are reduced by the proportion the valuation of the possessed past of the works to the contract sum and half the retention for that portion of the works is released.

·         A drawing should be used to identify the relevant part of possession.

Certificate of Non-Completion


·         The date for completion of construction works (or dates for completion of sections of the works) will agreed and set out in the contract particulars. However, it is not uncommon for delays to cause the completion date to be missed, that is, the works are not complete, and so a certificate of practical completion cannot issued by the date for completion.

 

·         Where the client is responsible for the delay, an extension of time may be granted, the completion date adjusted, and the contractor may be entitled to claim loss and expense.

 

·         Where the contractor is responsible for the delay, the client may be entitled to claim liquidated and ascertained damages (at a rate set out in the contract particulars).

 

·         In JCT SBC11 the contract administrator must issue the Contractor with a certificate of non-completion as a pre-requisite to claiming liquidated and ascertained damages. The certificate of non-completion gives formal written notice to the contractor that they have failed to complete the works described in the contract by the completion date that was last agreed (the original completion date may have been adjusted during the course of the works).

 

·         The contract administrator consider applications for extension of time before issuing a certificate of non-completion, and if there are subsequent extensions of time that result in the completion date being adjusted, and the contractor then fails to meet this adjusted date, a new certificate of non-completion must be issued

 

Rectification Period


·         The rectification period begins upon certification of practical completion and typically lasts six to twelve months.

·         During this period, the client reports any defects that arise to the contract administrator who decides whether they are defects in the works, or whether they are in fact maintenance issues.

·         Under clause 2.38.2, If the contract administrator considers that they are defects, then they may issue instructions to the contractor to make good the defects within a reasonable time.

·         It is the contractor's responsibility to identify and rectify defects, not the clients, so if the client does bring defects to the contractor's notice, they should make clear that this is not a comprehensive list of all defects

·         At the end of the defects liability period, the contract administrator prepares a schedule of defects, listing those defects that have not yet been rectified, and agrees with the contractor the date by which they will be rectified. The contractor must in any event rectify defects within a reasonable time

·         When the contract administrator considers that all items on the schedule of defects have been rectified, under clause 2.39 the CA will issue a certificate of making good defects. This has the effect of releasing the remainder of any retention and results in the final certificate being issued.

 

Final Certificate


·         The final certificate is certification by the contract administrator that the contract has been fully completed. It must be issued at the end of the defects liability period (set out in clause 4.15.1) and has the effect of releasing all remaining money due to the contractor, including any remaining retention.

 

·         The value of the final certificate will be based on the final account agreed by the cost consultant and the contractor. This means that all defects must have been remedied, all adjustments to the contract sum must have been agreed and all claims settled.

 

By final certificate stage the following certificates should have been issued:

·         Interim certificates at monthly intervals (Clause 4.9.1)

·         Practical Completion Certificate (Clause 2.30)

·         Certificate of Making Good (Clause 2.39)

 

·         The Final certificate must state the contract sum as adjusted under clause 4.3, which sets out all the deductions and additions to the contract sum.  The remaining half of the Retentions (the first half released at Practical completion) will be released at this stage.

·         Refer diagram Page 121 of Guide to SBC

 

Latent and Patent Defects


·         Latent defects are defects that do not become apparent until many years after the defects liability period has ended (as opposed to patent defects which are apparent).

 

Examples of common latent defects include:

·         Defective basement tanking allowing water penetration.

·         Inadequate wind-posts or wall ties causing movement damage to walls.

·         Under-strength concrete or misplaced reinforcement allowing movement damage to the structure.

·         Inadequate foundations causing subsidence of the building.

·         After the end of the rectification periods the building owner does not have a contractual right to insist that the contractor rectifies defects not notified during that period. Instead the employer must instead seek damages, for breach of contract, or for negligence. Limitation to liability 6 years or 12 years if signed as a deed.

 

Termination


·         Most forms of contract will include termination clauses, setting out the circumstances under which a contract may be terminated. When a contract is terminated, the parties to the contract are no longer obliged to perform their obligations under the contract.

·         In JCT SBC11, both the Contractor and Employer have a mechanism for terminating the contract under specific circumstances (listed under clause 8.4).  The termination can be initiated by the Employer in the event of specified defaults by the Contractor occurring prior to Practical Completion, insolvency of the Contractor or corruption.

·         Under clause 8.4.1, If a default occurs the CA should issue a warning notice. And if the default continues for longer than 14 days from the notice, the employer may terminate the employment of the Contractor by issue of a further notice within 21 days from the expiry of the 14 days (Clause 8.4.2)

·         All notices must be delivered by hand, sent by recorded signed for or Special delivery post.

·         Under contract clause 8.5.2 the contractor must notify the employer in writing in the event of liquidation or insolvency. In this event the Employer is given the option to terminate.

·         The contractor has a reciprocal right to terminate its own employment under clause 8.9.1 in the event of specified defaults of the employer.

 

 

 

Role of Contract Administrator


 

·         The role of the Contract Administrator is to administer the contract between the Employer and Contractor impartially. This role is often taken by the Architect, agreed in their appointment, however; it could also be taken by a Lead or Cost Consultant or Client Representative. 

 

·         Contract administrators are appointed by the client and usually act as the client's agent. When certifying or giving an assessment or decision, the administrator has to act honestly and reasonably and their decisions are open to challenge via the dispute resolution procedure unless the contract makes their decisions final and conclusive.

Role includes:

·         Inviting and processing tenders.

·         Preparing contract documents for execution.

·         Administrating change control procedures.

·         Issuing instructions such as variations, or relating to prime cost sums or making good defects.

·         Considering claims.

·         Preparing and issuing construction progress reports.

·         Co-ordinating and instructing site inspectors.

·         Agreeing commissioning and testing procedures.

·         Agreeing defects reporting procedures.

·         Ensuring that project documentation is issued to the client.

·         Issuing certificates of practical completion and interim certificates.

·         Collating and issuing schedules of defects.

·         Issuing the certificate of making good defects.

·         Issuing the final certificate.

 

No comments:

Post a Comment